Time & Work
Combined work, pipes & cisterns, alternating workers.
What's covered
This topic carries 23 questions in our bank, drawn from the SSC CGL syllabus and previous-year papers. Every question has a worked-out explanation.
PYQs by year
- SSC CGL 2025 14 questions
- SSC CGL 2024 5 questions
- SSC CGL 2023 3 questions
Sample questions
- Q1
12 men can build a wall in 15 days. How many men are needed to finish it in 9 days?
- Q2 • SSC CGL 2024
A can do a piece of work in 12 days and B in 18 days. Together they will finish it in:
- Q3 • SSC CGL 2023
A can complete a piece of work in 25 days while B can complete the same work in 30 days. They work on alternate basis, starting with A. Both A and B follow this pattern for 5 days and then A leaves the work. In how many days will B finish the remaining work?
Start the quiz above to see all questions and answers.